STATS Reports Successful Installation of Two Hot Tap BISEP™ Isolations on Crude Oil Pipelines

Friday, December 03, 2010 by STATS Group

BPTT has approached STATS to hot tap and insert a double block and bleed isolation plug in two 14in crude oil pipelines, located in the Galeota Point terminal facility. Maximum system pressure to be isolated in this operation was 20barg / 290psig.

STATS, after completing successful 14in tapping operations, has used its patented BISEP technology to achieve isolation on the piping system to allow for the tie-in of piping spools for the TSP metering project.

The entire intervention and isolation operation was carried out safely, while the system remained live and at full system pressure. STATS BISEP dramatically increases safety over traditional line stop technology by providing a fully verified double block and bleed isolation through a single hot tap penetration. This approach also significantly reduces time and costs. (Single fitting, welding, inspection, scaffolding, and crane costs).

Isolate pipeline using STATS 14in BISEP

STATS installed the BISEP and then performed validation tests on the tool to confirm successful double block and bleed isolation. After that, STATS issued an isolation certificate to the BP client.

Client performs valve change outs and tie-ins

On the successful isolation of the pipeline and isolation certificate issued, the BP client completes the required scope.

Remove BISEP

On completion of client work scope the new installations / valves and pipelines were pressure-tested against STATS BISEP. On completion of the test, the BISEP was unset and removed.

Install completion plug and blind flange

Using the hot tap machine, STATS installed a completion plug into the tee fitting, which allowed the removal of the slab valve. A ported blind was then fitted and pressure tested to successfully complete the scope.

Methodology

Weld on 14in split tees and pressure test: in this occasion STATS provided weld on fittings for this job application. The tees were welded by BP personnel on site with the presence of a STATS representative. Once the welding had passed inspection the tees where pressure tested by STATS personnel.

Slab valve installed and tested: STATS provided a fully certified and tested slab valve for the isolation work. Once the tees had been tested STATS personnel installed the slab valve and performed testing to confirm fully operational use.

Install hot tap machine and complete tapping operation: using STATS CHT1675A hot tap machine STATS personnel completed successful hot tapping operations.