X

Arad-Szeged Gas Pipeline

Project type

Natural gas pipeline

Location

Hungary-Romania

Order Year

2008

Construction Start

2009

Completion

August 2010

Investment

€68m

Operator

MOL Group (Hungarian section) and Transgaz (Romanian section)

Length

109km (total) 62km (Romanian section) 47km (Hungarian section)

Diameter

700mm

Design Capacity

4.5bcm

Operating Capacity

1.7bcm