Qatar Gas II Project, Ras Laffan, Qatar

Email-Icon
 
Print-Icon
 
Link-to-us
 
Related Projects
key facts
Key Data
Order year
2002
Construction started
2004-05 (pre-FEED 2002, FEED 2003)
Project type
Integrated LNG project
Location
Ras Laffan, Qatar
Estimated investment
$12.8bn
Completion
2007
Production capacity
30 billion cubic metres of gas per annum and 15.8mtpa of LNG (expected)

The Qatar Liquefied Gas Company Limited (Qatar Gas), a joint venture company set up by Qatar Petroleum and ExxonMobil Corporation, has expanded its facilities at the Ras Laffan industrial city natural gas liquefaction plant in Qatar.

The Qatar Gas II project is split between Qatar Petroleum (65%), ExxonMobil (18.3%) and Total (16.7%). The project provides a further two gas liquefaction trains each capable of processing in excess of 7.8mtpa of natural gas for export by LNG tanker.

In late 2004 ExxonMobil's determination to be the sole foreign partner in this key venture received a blow. Qatar Petroleum negotiated with the French oil and gas company Total for a stake in train B.

A $3.5bn deal was signed in February 2005, under which Total was to pay $1bn for a 16.7% stake in train B and to buy up to 5.2 tonnes per year of LNG from Qatar Gas II for 25 years. Total is to market its share of the LNG in Europe.

"The Qatar Gas II project is split between Qatar Petroleum (65%), ExxonMobil (18.3%) and Total (16.7%)."

The Qatar Gas II project was inaugurated in April 2009. It comprises three offshore platforms, two LNG trains, five storage tanks, two loading berths, a fleet of 14 LNG ships and a receiving terminal in Milford Haven, Wales.

A new AP-X liquefaction process technology from Air Products has been put into operations at the Qatargas II project expansion in July 2009.

The new technology is likely to raise the LNG production capacity of each train over the current generation of LNG process trains by around 50%.

Investment and progress

The project investment has been estimated at $12.8bn and will exploit the large gas reserves of the Qatar north field, which has estimated recoverable natural gas resources in excess of 900 trillion cubic feet (9.3% of the world's proven reserves). The contracts for the work were awarded in late 2004 and construction work was started in early 2005.

The Pre-front end engineering and design (FEED) activities for the project were completed in 2002 and FEED started in June 2003. At the production end of the project, where the gas wells are drilled, data and appraisal wells commenced in May 2004.

Qatar gas project construction

The integrated project involves the construction of two of the largest LNG trains in the world (trains four and five). Train four was commissioned in the fourth quarter of 2005. Train five started LNG production in September 2009. Each of these trains will equal the combined production of the existing trains one, two and three of Qatar Gas phase one.

The LNG will be exported to a dedicated receiving terminal still being constructed at South Hook Terminal in Milford Haven, West Wales, UK. The project will process 30 billion cubic metres of gas per annum and will produce 15.8mtpa of LNG, 6mmta of condensates and 1.7mmta of propane / butane.

Construction of the South Hook terminal is being carried out in two phases. Phase I operations commenced during October 2009 and phase II is expected to be completed in the first quarter of 2010. On completion, the terminal will have a total annual processing capacity of 15.6 million tonnes of LNG and will be able to offer 21 billion cubic metres per annum of gas to National Transmission System. At present, the terminal's first phase can process 10.5 billion cubic metres per year.

Qatar Gas II project contractors

The $4bn contract for the engineering and construction of the LNG train portion of the project was awarded to a joint venture company consisting of Technip SA of France, Snamprogetti of Italy and Chiyoda Company of Japan.

"The project will process 30 billion cubic metres of gas per annum."

The two new trains (LNG four and five) are being installed in the confines of the existing Qatar Gas facility and so will benefit from the existing infrastructure from the Qatar Gas phase I plant.

Qatar Gas II is using the latest LNG technology from Air Products of the USA, which by taking advantage of better economies of scale, cuts plant unit and shipping costs by 30%.

Three wellhead platforms and two 36in pipelines are also required to produce and transport the 2.8bscfd of gas along with the associated condensate. These facilities are being constructed under a $500m contract awarded to the National Petroleum Company of the UAE. The total fluids and gas will be transported to the Ras Laffan onshore facilities in a wet scheme.

Invensys Singapore were awarded an $8m automation contract for the LNG train five production and utilities units in Qatar, using Foxboro and Triconex systems with options for expansion of the storage and loading facilities.

The project scope includes Foxboro-brand I / A Series process control systems, Triconex TMR safety instrumented systems and fire and gas protection systems, plus associated project engineering services.

LNG receiving facilities

The contract for the construction of the facilities at the receiving terminal in Milford Haven, UK, was awarded in mid-November 2004. The Chicago Bridge and Iron Company (Woodlands, Texas) was awarded a lump sum turnkey contract for an estimated $700m to build a grassroots LNG import terminal.

The facility will be operated in a 70 / 30 split by South Hook LNG Terminal Company Ltd, a British company owned by Qatar Terminal Company and ExxonMobil Qatar Gas II Terminal Company. The Qatar Petroleum Gas Development Group is also involved in project management.

Invensys has previously successfully implemented the process control systems, safety systems, and many additional systems for Ras Laffan LNG trains one and two, and was awarded the expansion project for LNG train three, train four and associated projects.

Shipping contracts

A fleet of 16-18 LNG carriers are being constructed to support shipping of the lean LNG to the dedicated UK terminal. The orders for new LNG tankers were placed in mid-November 2004.

"A fleet of 16-18 LNG carriers are being constructed to support shipping of the lean LNG to the dedicated UK terminal."

Three South Korean shipyards were commissioned to build eight state-of-the-art tankers that will be 50% larger than conventional LNG ships.

Daewoo Shipbuilding and Marine Engineering will produce four 210,000m³ tankers at a cost of around $875m, while Hyundai Heavy Industries and Samsung Heavy Industries took orders estimated at $450m to build two vessels each.

The remaining eight LNG transport ships will be provided under a series of 25-year timecharters with two consortiums, ProNav-Commerzbank-Qatar Gas Transport Company and Overseas Shipholding Group-Anglo Eastern-Qatar Gas Transport Company.

These state-of-the-art vessels range in size from 209,000m³ to 216,000m³ and will be on average 50% larger than conventional LNG ships, thus making transportation more economical.

Financial arrangements

Qatar Liquefied Gas Company Ltd and South Hook LNG Terminal Company Ltd both signed financing documents securing funds to execute the project in November 2004 ($6.5bn and £600m respectively).

In total, $7.6bn was raised from 57 financial institutions, which is the first ever financing on a full LNG chain-integrated basis.

Financing the agreement involved a bank facility, an Islamic finance facility, export credit funding and an ExxonMobil facility. It is likely that as the project nears completion, the lenders may refinance the loans and investors will see some bond issues coming from the project.

Part of the process involved the formation of a new company (South Hook LNG Terminal Company Ltd) to manage the LNG importation, terminal operations and sales of natural gas to ExxonMobil Gas Marketing Europe (100% ExxonMobil owned) which will resell the gas to UK markets. Qatar Petroleum owns 70% of the new company, with ExxonMobil holding the remaining 30%.

At the end of December 2004 Total entered into the project having negotiated a stake in the capacity of the new liquefaction facility (trains four and five) at Ras Laffan. Total would like to secure 5mtpa of the 15.6mtpa.



Expand Image Expand Image
Qatar Gas is expanding its facilities at the Ras Laffan industrial city natural gas liquefaction plant in Qatar.



Expand Image Expand Image
The LNG import terminal, which is being constructed at Milford Haven, Wales, UK.



Expand Image Expand Image
One of the super LNG transport vessels being constructed to support shipping of the lean LNG to the dedicated UK terminal.



Expand Image Expand Image
The vessels range in size from 209,000m³ to 216,000m³ and will be on average 50% larger than conventional LNG ships, thus making transportation more economical.



Expand Image Expand Image
The project will exploit the large gas reserves of the Qatar North Field.



Expand Image Expand Image
The two new trains (LNG 4 and 5) are to be installed in the confines of the existing Qatar Gas facility.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  

Suppliers
JorinModulift

Newsletter Sign-Up
For all the latest news in the hydrocarbons industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Industry News
Gallery
Events & Exhibitions
Newsletter
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the hydrocarbons industry