Sabine Pass LNG Terminal

Project Type

LNG Terminal

Location

Cameron Parish, Louisiana, US

Construction Started

March 2005

Completed

April 2008 (Phase I) 2009 (Phase II)

Total Send Out Capacity

4bcf/d

Storage Capacity

16.8bcf

Area

853 acres

Owner and Operator

Cheniere Energy

EPC Contractor

Bechtel Corporation

Storage Tanks Contractor

Mitsubishi Heavy Industries America and Zachry Construction Corporation

Bulkhead Design and Construction Services

PND

Equipment Supplier

Emerson

Technology Provider

Invensys Process Systems