West-East Gas Pipeline Project

Project Type

Natural gas pipeline

Construction Started

WEPP I: 2002; WEPP II: 2008; WEPP III: 2014

Completion

WEPP I: 2004; WEPP II: December 2012; WEPP III: 2015

Commissioned

WEPP I: January 2004, WEPP II: June 2011; WEPP III: 2015

Estimated Investment

WEPP I: $5.7bn; WEPP II: $22bn; WEPP III: $19.9bn (estimated)

Developer and Owner

PetroChina

Project Management

China National Petroleum Corporation (CNPC)

Pipe Suppliers

Shandong Shengli Steel Pipe, Baosteel, Maanshan Iron and Steel, Taiyuan Iron and Steel

Contractors and Suppliers

GE Oil and Gas, RMG Regel + Messtechnik, Converteam, Nortel, Rolls-Royce, Elster-Instromet, Lincoln Electric Company, Cameron, Nordstorm, Caterpillar, Emerson, Universal Ensco

WEPP II Operations Management

Honeywell

Output

WEPP I: 17bcm; WEPP II: 30bcm; WEPP III: 20bcm (planned)

Pipeline Diameter

WEPP I: 1,016mm; WEPP II: 1,219mm
Expand

Free download worth over $5000
Download our 2019 Technology, Media and Telecoms Predictions Report

Worth up to $5,850

In this report, we look at the 30 big tech themes for 2019, identifying winners and losers for each theme. This report will impact all industries helping:

  • CEOs/Senior Staff: in all industries understand the disruptive threats to their competitive landscape
  • Investors: Helps fund managers focus their time on the most interesting investment opportunities in global TM
Close