Escravos Gas-to-Liquids Project, Niger Delta, Nigeria

Email-Icon
 
Print-Icon
 
Link-to-us
 
Related Projects
key facts
Key Data
Order year
1998 (feasibility study)
Construction started
2005
Project type
Gas-to-liquids plant
Location
Escravos, Nigeria
Production
34,000bpd
Estimated investment
$1.7bn (N226.1bn)
Completion
2011

Chevron Nigeria Limited (CNL) (75% share) along with the Nigerian National Petroleum Company (NNPC) (25% share) is constructing the 34,000 barrel per day (bpd) Escravos Gas-to-Liquids (EGTL) plant in Escravos, Nigeria (this is expected to be expanded to a 120,000bpd capacity within ten years of completion).

The Escravos site is located about 100km southeast of the Nigerian capital Lagos. The plan will make use of the rich gas resources of the Escravos field, which can now produce 340 million cubic feet of dry gas per day along with 1,200 barrels of condensate and 8,500 barrels of LNG.

EGTL design and development

With EGTL as the first project using its technology and technical expertise, Sasol Chevron will work on the design and development of EGTL and will provide management, operating and technical services to the project owners. Sasol Chevron will also market products from EGTL.

The $1.7bn (N226.1bn) EGTL project will form an integral part of the owner's overall gas use strategy that includes domestic natural gas sales, regional natural gas sales through the West Africa Gas Pipeline (WAGP), and international sales of GTL products.

"The EGTL project is expected to be completed in 2011 and will be operational in 2012-13."

In October 2009, the Senate committee on Gas recommended reduction of the cost of project which had escalated to $5.9bn from $1.7bn. The initial estimated cost of the project was revised twice and reached $5.9bn. Due to the increase in costs, the project is expected to be completed in 2011 and will be operational in 2012-13.

The proposed GTL plant will be capable of converting natural gas into premium environmentally friendly fuel, diesel and GTL naphtha products. Europe will be the primary market for all fuel products from the Nigerian plant, although some products may be sold in the USA.

Although the project is situated in a politically sensitive area, both Chevron and Sasol are confident about bringing the project to fruition by 2011. Already, Sasol and Chevron have sent 200 Nigerians to South Africa on a 26-month training course at the Sasol plants in Secunda and Sasolburg.

Fischer-Tropsch and Isocracking technologies

Sasol Chevron will provide the project with the leading technologies of the two companies, Sasol's proprietary Fischer-Tropsch Technology and Chevron's proprietary Isocracking technology.

Sasol is a recognised leader in state-of-the-art Fischer-Tropsch technology and has been actively involved in developing the technology for over 50 years. The Isocracking process is used to upgrade waxy syncrude to yield a lighter premium grade fuel that contains no sulphur or aromatics.

Escravos GTL plant

The Escravos GTL project will convert over 300 million cubic feet of natural gas a day to GTL diesel and GTL naphtha. The GTL plant will be located adjacent to the CNL Escravos Gas Plant – phase I (EGP-1).

"The GTL plant is designed to process GTL products like low-sulphur GTL diesel."

This plant processes about 150 million cubic feet of gas per day and produces LPG for sales to international markets and pipeline quality gas for domestic uses.

The EGP-1 project, which cost $550m, was completed in 1997. The NNPC / CNL joint venture is expanding the gas plant (EGP-2) and plans to construct an additional plant (EGP-3) to ensure sufficient gas supply for the EGTL and the WAGP.

Feasability studies

A pre-feasibility study in April 1998 started the ball rolling for the EGTL project; this was followed by a more in-depth engineering feasibility study to confirm the design configuration and economics.

After the successful completion of the feasibility study, EGTL entered with front-end engineering and design (FEED) in July 2001. This was completed in 2002. The project will be executed under a lump-sum engineering, procurement and construction contracting strategy and first production is expected in 2012.

The environmental impact and socio-economic assessments were completed and project-critical path site preparation activities commenced in early 2002. The two layers of sand have now been placed on the EGTL project site where the process units are being constructed. Approximately 2,900,000m³ of sand was placed on the EGTL project site.

EPC contracts

In April 2005 the NNPC awarded the contract for the EGTL project to a consortium consisting of JGC of Japan; Kellogg, Brown and Root (KBR) of the USA and Snampogetti of Italy.

"The Escravos site is located about 100km southeast of the Nigerian capital Lagos."

The GTL plant is designed to process GTL products like low-sulphur GTL diesel, GTL naphtha and Liquefied Petroleum Gas (LPG), and thus eliminate the high incidence of gas flaring in Chevron Texaco's area of operation.

Another key area of the contract involves the construction of a mini refinery to be used for fuelling boats, helicopters, fixed-wing aircraft, drilling rigs and onshore / offshore facilities.

The mini refinery will also service floating petroleum filling stations to be introduced in the Niger Delta region. Julius Berger Nigeria has completed construction the initial six floating stations under a contract received in 2005.

Acergy SA secured a $500m contract for gas development plan of the project in October, 2009. The contract includes engineering, fabrication, procurement, transportation, installation, tie-in and commissioning of the plant. It covers the procurement and installation of pipelines of about 130km length and assembly along with installation of 15 risers. The contract also includes installation of three Subsea tie-ins and 40 crossings.



Expand Image Expand Image
The Escravos gas-to-liquids project site, with a representation of the facility overlaid, shows room for expansion if required.



Expand Image Expand Image
The Escravos site prior to construction (sand base laid down).



Expand Image Expand Image
Africa has a large reserve of gas – 10.2 trillion cubic metres.



Expand Image Expand Image
The Escravos GTL project will convert over 300 million cubic feet of natural gas a day to GTL diesel and GTL naphtha.



Expand Image Expand Image
A schematic of the gas-to-liquids process.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Newsletter Sign-Up
For all the latest news in the hydrocarbons industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Industry News
Gallery
Events & Exhibitions
Newsletter
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the hydrocarbons industry