![]() | ||
Snohvit LNG Export Terminal, Melkoya Island, Hammerfest, NorwayThe Snohvit LNG project is being constructed to exploit the resources of three gas fields in the Barent Sea; Snohvit, Albatross and Askeladd (240m to 345m deep), which lie about 140km northwest of Hammerfest in Norway. "The gas production system will be one of the first in Europe to use a subsea production platform."
These fields, which were first discovered in the 1980s, have estimated reserves of 300 billion m³ of LNG and 20 million m³ of condensate. The gas production system will be one of the first in Europe to use a subsea production platform, which will feed gas via 160km of pipeline to a new processing plant on Melkoya Island near Hammerfest. The project is being led by Statoil as part of a consortium of eight companies. The consortium consists of Statoil (22.9%), Petoro (30%), TotalFinalElf (18.4%), Gaz de France (12%), Norsk Hydro (10%), Amerada Hess (3.26%), RWE-DEA (2.81%) and Svenska Petroleum (1.24%). The LNG processing project has required finance of more than $5.3 billion (NOK51.3 billion); part of the finance is being provided by the Japanese Bank of International Commerce (JBIC). The project was authorised by the Norwegian Parliament in 2002 (subject to some clarification of the terms of distribution of revenues and taxes) and construction on the project began in late 2003. The facility is due to come on-stream in the second half of 2006 and be used over the next 25 years. PRODUCTION CAPACITY The production capacity of the new single train facility will be 4.3 million t/yr (equivalent to approximately 5.6 billion m³ of LNG). Supply contracts have been agreed to date with customers in East Coast US (El Paso) and Spain (Iberdrola) accounting for 4 million t/yr of the capacity (the remaining capacity and any future expansion may well go to Gaz de France). "The production capacity of the new facility will be 4.3 million t/yr."
The unprocessed gas arriving at the LNG processing facility will contain between 5% and 8% carbon dioxide; this will be separated out at the processing and liquefaction facility and returned via a separate 160km pipeline for storage beneath the seabed (2,600m below the sea bed on the edge of the reservoir in the 45m to 75m thick Tubasen sandstone formation) thus preventing undue pollution and allowing Norway to adhere to the Kyoto treaty. The energy efficiency of the liquefaction facility will be 70% which is the best yet achieved in any plant of this kind across the world (the compressor will operate with an efficiency of 230kWh per ton of LNG). CONTRACTORS AND CONSTRUCTION The management, engineering, procurement and construction contract (€380 million) was awarded to Linde AG for the provision of key equipment for the LNG terminal. Linde will use MFC liquefaction technology developed jointly by themselves and Statoil (Air Products and Philips are also to contribute technology to the liquefaction train). The instrumentation for the facility is being supplied by Parker Instrumentation. Aker Kvaerner was awarded a contract in early 2005 (worth an estimated NOK1 billion) for important completion work at the LNG facility at Melkoya Island. This contract will involve Aker Kvaerner Elektro (for electrical and instrumentation installation), Kaefer IKM for scaffolding, insulation and surface treatment and Aker Stord for management of this section of the project which involves installation and integration of the liquefaction/process equipment into the island infrastructure. Aker Stord was awarded the main hook-up and installation contract on Melkoya Island in 2003 and has been at work preparing the infrastructure and equipment on the island. Aker Kvaerner will have over 800 personnel working on the island over the first half of 2006 so that the project can be completed on schedule. LIQUEFACTION / PROCESS BARGE"The liquefaction plant will be borne and operated on a gas liquefaction barge."
The heart of the LNG facility, the liquefaction plant, will be borne and operated on a gas liquefaction barge, in the final stages of construction at the Spanish shipyard group Izar Construcciones Naval (Dragados yard) in Cadiz. The barge construction contract is worth an estimated NOK170 million. The process barge will measure 9m H × 154m L × 54m W. This process barge approach was chosen as it greatly reduces the need for steelwork on Melkøya Island, necessitates a compact efficient design, allows prefabrication of modular components off-site in a convenient dry-dock situation and, most importantly, gives cost savings as well as higher productivity compared with constructing the plant on-site. Following completion of the barge in May 2005 it was towed to an outfitting yard where 24,000t of process equipment for the gas liquefaction plant was installed on the deck. The barge was then transported to Melkøya Island in July 2005 on a heavy-lift vessel and installed in a custom built dock. The completion work for the barge on the island is due to be completed by the end of August 2006. INSTRUMENTATION COMPONENTS AND SUB-SYSTEMS Parker Instrumentation is supplying all of the instrumentation components and sub-systems for the Snohvit LNG project. They will provide over 1,000 H-series manifolds, 20km of conventional and heat race tubing and many thousand twin-ferrule A-LOK compression tube fittings. The components will be supplied fabricated in 316 stainless steel and, for areas where corrosion is a major problem (sea water cooling systems), in 6Mo (6% Molybdenum steel). Parker will also use their Supracase process to harden the ferrules of the fittings and avoid the affects of corrosion. The instrument enclosures provided by Parker will be weather proof and equipped with antifreeze systems to allow them to operate at temperatures below -25°C. LNG, CONDENSATE AND LPG EXPORTS"Annual exports are anticipated to be 5.75 billion m³ of LNG, 747,000t of condensate and 247,000t of LPG."
The consortium has estimated that they will need four 145,000m³-capacity carriers to deliver the LNG to receiving terminals in the US and southern ports of Europe (investment for these new ships will approach NOK5.4 billion). It is also estimated that there will be 70 cargos of LNG per year shipped out from the Melkøya facility. The annual exports are anticipated to be 5.75 billion m³ of LNG, 747,000t of condensate and 247,000t of Liquefied Petroleum Gases (LPG). The total investment will include NOK34.2 billion for field development, pipeline and land plant and NOK5.4 billion for ships. CONSTRUCTION OF THE LNG TANKS The Snohvit project has required the construction of two LNG tanks, one condensate tank and one LPG tank at the gas processing complex on Melkøya Island. The respective tanks have the following capacities and dimensions:
DYWIDAG Systems International (DSI) was responsible for the supply and installation with stressing and grouting of a total of 1,650t horizontal and vertical DYWIDAG post-tensioning tendons with accessories in the construction of the tanks to allow them to withstand the extreme conditions. The weather conditions during the construction were of an extreme arctic nature. The tank walls were constructed by means of a slip formwork with a performance of 2m/24h within a few weeks. A particular challenge was the installation of the vertical tendons with 12 strands. The vertical tendons of the tanks are typical U-shaped or loop tendons. A loop tendon consists of two vertical tendons, which are connected at their bottom ends in the foundation by a 180° arc. In spite of a maximum tank wall-height of 40m and an arc radius of only 1m the installation of the loop tendons by pushing single strands was carried out without any problems. GAS PIPELINE"Each gas pipeline section weighs 8t to 10t, with a total of 11,000 sections making up the main line."
Work is currently nearing completion on laying the main pipeline to carry the gas from the Snøhvit fields to the LNG plant. In April 2005 the Solitaire laybarge started laying the 143km pipeline from the western side of Melkøya. The vessel has continued towards the Snøhvit field at a rate of 3km to 6km per day. On board the Solitaire, 12.2m-long sections of pipe are welded together in a continuous process. The sections are fed out through an opening in the stern of the laybarge, ensuring that the main pipeline is curved correctly during the laying. The Solitaire is supplied with new pipe by three pipe transport boats which provide a shuttle service between the laybarge and the pipe storage area at Polarbase outside Hammerfest. The 28 in-diameter line pipe is made of steel with an outer coating of reinforced concrete. Each pipe section weighs between 8t and 10t, with a total of 11,000 sections making up the main line. Laying the main pipeline was completed in mid-2005. ADDITIONAL SHIPPING 'K' Line (Kawasaki, Kisen, Kaisha Ltd) was taken on as the partner of Statoil ASA in the Snohvit LNG Coastal Transportation Project. In turn 'K' Line selected OSM Ship Management AS to be their Norwegian project partner. The project involves the delivery of LNG from the Snohvit LNG Plant to the coastal cities in Norway and its neighbour countries by small LNG vessels (this will account for the remainder of the capacity of the LNG facility). The parties have worked with LNG Norge (a subsidiary of Statoil). The idea was then developed into a long-term charter for two 140,000 cbm (Moss-Rosenberg tank type) LNG carriers worth NOK3 billion ($337.2 million). 'K' Line will, together with Statoil, be the owner/operator of the vessels, which will be delivered in late 2006 or early 2007. The vessels will be engaged in domestic transportation first, but may expand their activity to ports in neighbouring countries. In 2004 the Snohvit partners also signed a deal with Leif Hoegh and Co and Misui OSK lines for one vessel to serve the project during a 20 year charter. The ship is being built at Mitsubishi Heavy Industries and is due to be delivered in late 2006. In addition TotalFinaElf and Gaz de France have commissioned their own vessels to transport their share of the gas.
|
![]() The Snohvit gas production system will be one of the first in Europe to use a subsea production platform. | |
![]() The Snohvit LNG project on Melkoya Island is being constructed to exploit the resources of three gas fields in the Barent Sea (Snohvit, Albatross and Askeladd) which have estimated reserves of 300 billion m³ of LNG and 20 million m³ of condensate. | ||
![]() LNG liquefaction process diagram. | ||
![]() LNG compressor component. | ||
![]() Computer rendering of the LNG facility on Melkoya Island. | ||
![]() The heart of the LNG facility, the liquefaction plant, will be borne and operated on a gas liquefaction barge. | ||
